Frankton Beach WWPS Flow Meter

Queenstown

Category: Drainage


Expose 560mm PE line outside of pump station. The line was the main line from Queenstown, situated next to Lake Wakatipu at Frankton.

  • Cut in and fit stub flanges.
  • Install magflow meter & valve in a 1200mm manhole. Conduit from manhole chamber back to pump station for signal cable.
  • Backfill and reinstate.

Location: Frankton Road - Queenstown
Awards: Finalist at 2015 CCNZ Otago Hynds Construction Award
Client: Queenstown Lakes District Council
Key Personnel: Stuart Pile - Veolia
Category: Drainage
Contract Value: $23,745
Timeframe: Jul 2014


Services provided

  • Drainage

An outstanding job. I am delighted with the outcome. We had a number of senior management visit the site when they were down here recently and whilst they didn't pass too much comment on the actual install, the important issue was that the job was completed safely.

Stuart Pile

Stuart Pile

Veolia